Terminal Facilities
Client:
Marcus Hook, PA, U.S.
Sunoco Logistics Partners L.P.
Location:Marcus Hook, PA, U.S.
Fluor is providing procurement, construction and construction management services for the Sunoco Logistics Mariner East 2 project at its Marcus Hook Industrial Complex on the Delaware River in Pennsylvania. Upon completion of new terminal facilities to store, chill, process and distribute propane, butane and ethane for domestic use and export, Mariner East 2 is anticipated to provide up to an extra 275,000 barrels-per-day of natural gas liquids (NGLs) for distribution.
Fluor’s scope has expanded to procurement, commissioning and construction by leveraging our integrated solutions approach.
Fluor’s scope has expanded to procurement, commissioning and construction by leveraging our integrated solutions approach.
Client's Challenge
The Marcus Hook Industrial Complex includes terminal and storage assets and related commercial agreements. The facility can receive NGLs via marine vessel, pipeline, truck and rail, and can deliver via marine vessel, pipeline and truck.
The Marcus Hook Industrial Complex currently serves as an off-take outlet for Sunoco’s Mariner East 1 system. The Mariner East project transports NGLs from Western Pennsylvania, West Virginia and Eastern Ohio to destinations in Pennsylvania, including the Marcus Hook Industrial Complex. The project footprint covers 19 acres.
Source: Sunoco Logistics website
The Marcus Hook Industrial Complex currently serves as an off-take outlet for Sunoco’s Mariner East 1 system. The Mariner East project transports NGLs from Western Pennsylvania, West Virginia and Eastern Ohio to destinations in Pennsylvania, including the Marcus Hook Industrial Complex. The project footprint covers 19 acres.
Source: Sunoco Logistics website
Solution
Fluor will construct new terminal facilities for the Sunoco Logistics Mariner East 2 project at its Marcus Hook Industrial Complex. Upon completion, Mariner East 2 is anticipated to provide up to an additional 275,000 barrels-per-day of NGLs for distribution to local, domestic and international markets.
The Mariner East 2 project comprises the following major elements:
Fluor, Sunoco Logistics and contractors are using Fluor Site ConnectSM, our project-wide communication platform to access key information throughout the project site, contributing to a largely paperless jobsite.
More than 2,200 craft personnel support the project representing Fluor, building trades and local unions. Fluor’s direct-hire craft peaked at 196 in November 2016, and Fluor staff peaked at 143 in January 2017.
The Mariner East 2 project comprises the following major elements:
- Four product storage tanks (by Third Party)
- Refrigeration equipment
- Dock mounted load out equipment and piping modules (by Third Party)
- Dock rehabilitation
- Substation (by Third Party)
- Two incoming feeders from the new substation
- New firewater supply and distribution system
- In-plant pipe runs and supports
- Incoming pipeline for NGL feedstock
- Electrical and instrumentation
- Cooling water tower
- Flare system
Fluor, Sunoco Logistics and contractors are using Fluor Site ConnectSM, our project-wide communication platform to access key information throughout the project site, contributing to a largely paperless jobsite.
More than 2,200 craft personnel support the project representing Fluor, building trades and local unions. Fluor’s direct-hire craft peaked at 196 in November 2016, and Fluor staff peaked at 143 in January 2017.
Conclusion
Fluor provides procurement, commissioning and construction services as part of its integrated solutions approach for Sunoco Logistics’ Mariner East 2 project at its Marcus Hook Industrial Complex in Pennsylvania. Upon completion of the new terminal facilities, Mariner East 2 is anticipated to provide up to an additional 275,000 barrels-per-day of NGLs.